4 Weekly Filter
Ever wondered how to setup a view/filter in MS Project to show any task that is in-progressĀ or to commence within the next 4 weeks? Here is how:
- Navigate to Project | Filtered For | More Filters
- Click on New Filter
- Define the filter as follows:

The Filter Form allows us to define a filter for “any activity that has not yet finished, but should have already started” or “any activity that is due to start between the 1/5 and the 31/5″ - Click on OK
- Click on the newly created filter, and click on Apply. This filters the currently selected view in MS Project.