4 Weekly Filter

Ever wondered how to setup a view/filter in MS Project to show any task that is in-progressĀ or to commence within the next 4 weeks? Here is how:

  1. Navigate to Project | Filtered For | More Filters
  2. Click on New Filter
  3. Define the filter as follows:


    The Filter Form allows us to define a filter for “any activity that has not yet finished, but should have already startedor “any activity that is due to start between the 1/5 and the 31/5″

  4. Click on OK
  5. Click on the newly created filter, and click on Apply. This filters the currently selected view in MS Project.